Current Projects

Intersection Roundabout at SW Butler Rd. and SW 150th


WAMPO Federal Aid STP Roadway Reconstruction - SW Butler Rd. from 0.5 mile South to 0.5 mile North of SW 150th St.

Be advised that beginning Monday, May 4th, 2020, the major road improvement and roundabout project on SW Butler Rd at SW 150th St located north of Rose Hill will begin construction.  The entire roadway and intersection will be closed to all through traffic beginning that week. 

No Traffic will be able to go through the intersection of SW Butler Rd. and SW 150th St from any direction once the roadway is closed.  2 detour routes will be marked for traffic to use.  Please see the attached detour route information and construction phasing plan for additional information.

The entire project will be under construction for up to 10 months weather permitting.  The project is tentatively planned to be built in 2 phases.  During Phase 1, the roundabout will be constructed and all the roadway improvements on SW 150th St. will be completed.  At the end of phase 1, SW 150th St will be reopened to all east and west traffic only.  During Phase 2, construction of roadway improvements on SW Butler Rd will be completed.  The intersection will still be closed to all traffic on SW Butler Rd. and most local traffic access from SW Butler Rd will be limited or restricted.  At the end of Phase 2, the entire project including the new roundabout will be opened to traffic.  Project detour map and phasingSienna Ranch/Paul's Valley Access map and phasing.

Bridge Replacement on SW Haverhill Rd.


Bridge replacement on SW Haverhill Rd. over the Little Walnut River, approximately 8.3 miles North of Smileyberg.  Schedule for replacement starting April 20, 2020.  The road will be closed during construction.  Construction is expected to take approximately 8 months. The official detour route for the project is from the junction of SW Haverhill Rd US-54/400, go west on US-54/400 to US-77 At Augusta, then use US-77 south from Augusta to SW 170th St., then use SW 170th St. east to SW Haverhill Rd and vice-versa.

Culvert Letting No. 74 - Reinforced Concrete Box Culvert


*NE 10th St. is closed between NE Ellis Rd and NE Price Rd in Prospect Township.  Road should reopen by the end of May 2020.

*SE Flinthills Rd between SE 40th St and SE 50th St approx. 3.7 miles south of US-54 at Rosalia.  Road is scheduled to close Wednesday, May 20th for approximately 6 weeks.  For the local detour, sue SE 30th St. east 1 mile to SE Gray Rd., south 2 miles on SE Gray Rd to SE 50th St., then west 1 mile on SE 50th St to SE Flinthills Rd and vice-versa.

SW Ohio Street Rd surface recycle and hot-mix overlay from SW 70th St. to K-254 Hwy  


This project is scheduled to begin by late summer.  The road will be open to 1 lane traffic with the use of a pilot car during the day.  Check back later for an updated construction schedule. 

2020 County Road Crack Seal Program


Crack Seal Program.  Please refer to the 2020 Project map for project locations.  Work is ongoing and in progress.  Road will be open to traffic during construction.

2020 County Road Patching Program


Road Patching Program.  Please refer to the 2020 Project map for project locations.  Work is ongoing and in progress.  Road will be open to traffic during construction.

County Road Paint Striping - Countywide (2020)


Beginning late summer 2020, County Contractor will be paint striping road centerline and edge stripes on asphalt surface County roads throughout the entire County.   Striping work will start on all new chip seal roads from 2020 and follow with roads that have been previously chip sealed.  

***BE AWARE - Do not drive over freshly applied paint immediately behind the paint striping truck.  Fresh paint can be picked up on tires and splattered in the tire wells and the lower body panels of vehicles.  Please be patient when trying to pass the paint rig.***